Road Construction Update For Those Wondering

North White Street at Cedar

 

The City of Carrollton’s Engineer, Tommy Holland sent us this information below about the road closures and various construction projects across the Downtown area lately. Be sure to follow our new Twitter account for the latest road issues. www.twitter.com/carrolltonroads

An 8 inch water main is being installed along N White St from Cedar to Newnan St (the main will also be installed from Newnan St to West Ave). Also, an 8 inch water main will be installed along N Coleman (from Cedar St to Newnan St). The water main upgrade (from the existing 4 inch to 8 inch) will provide better fire flow and water quality.

The existing 8 inch was located intersection at N White and Cedar St; therefore, the intersection had to be closed for one day to make the tie-in and lay the water main across the intersection. 

Tommy Holland – City of Carrollton Engineer

 

 